Armada Nowlit Wabasca / Hoole Data Centre
- Capacity
- 50 MW
- Investment
- Not publicly confirmed
- Score
- 25 / 100
- Checked
- Sep 11, 2026
Capacity basis: Announced data-centre capacity (MW)
DC Intel assessment
Speculative
Why
Named 50 MW crypto/data-centre concept tied to local gas assets and municipal engagement.
Risk
Related 9.5 MW plant applications closed without approval and do not support the announced 50 MW; no construction/operation confirmation.
Watch
Approved generation/power source and formal development permit.
Power strategy
Natural-gas power from Hoole assets proposed; no approved 50 MW supply demonstrated.
An AESO request is not an allocation.
Score
Sponsor Quality 6 / 15
Site & Approvals 6 / 20
Power Certainty 4 / 25
Commercial Commitment 3 / 20
Execution Evidence 6 / 20
Total 25 / 100
Scoring method. Not a credit rating or investment advice.