Bitdeer Fox Creek

Bitdeer Technologies Group M.D. of Greenview No. 16 Under construction Highly Credible
Capacity
100 MW
Investment
~US$155M
Score
88 / 100
Checked
Sep 11, 2026

Capacity basis: Approx. computing capacity (MW)

DC Intel assessment

Highly Credible

Why

Groundbreaking completed; approved 101.133 MW on-site gas plant and 99 MW AESO interconnection; experienced digital-infrastructure operator with disclosed capital plan.

Risk

Current planned workload is cryptocurrency, with AI/HPC optionality; schedule has moved and final economics depend on compute markets.

Watch

Construction progress and Q4-2027 energization.

Power strategy

101.133 MW dedicated natural-gas plant plus 99 MW AESO grid interconnection.

An AESO request is not an allocation.

Score

Sponsor Quality 13 / 15
Site & Approvals 18 / 20
Power Certainty 23 / 25
Commercial Commitment 14 / 20
Execution Evidence 20 / 20

Total 88 / 100

Scoring method. Not a credit rating or investment advice.