Projects

Data District Olds Facility

Technologies New Energy / Data District Town of Olds Proposed Early-Stage
Capacity
55 MW
Investment
Part of C$1.26B four-site Phase 1 program
Score
52 / 100
Checked
Sep 11, 2026

Capacity basis: Announced facility capacity (MW)

DC Intel assessment

Early-Stage

Why

Land has been acquired and local economic-development/site-readiness work is underway; project is part of a named multi-city Alberta program.

Risk

No formal development/regulatory application was confirmed in the latest public local update; power and customer commitments are limited.

Watch

Formal municipal application, utility/power agreement and construction financing/customer.

Power strategy

Alberta grid / FortisAlberta distribution indicated.

An AESO request is not an allocation.

Score

Sponsor Quality 9 / 15
Site & Approvals 14 / 20
Power Certainty 10 / 25
Commercial Commitment 7 / 20
Execution Evidence 12 / 20

Total 52 / 100

Scoring method. Not a credit rating or investment advice.

Sources

Checked Sep 11, 2026

Operations assurance