Goldfinch Technology Park Data Centre
- Capacity
- 950 MW
- Investment
- Not publicly confirmed
- Score
- 61 / 100
- Checked
- Sep 11, 2026
Capacity basis: AESO connection request (MW)
DC Intel assessment
Probable
Why
Serious infrastructure developer; County adopted the area concept plan/rezoning framework and AESO P3102 is active. Land-use progress is tangible.
Risk
950 MW is a connection request, not a grid allocation; no operator/tenant, FID or final development permit yet.
Watch
Development permit, power solution / AESO milestone and tenant commitment.
Power strategy
Proposed Alberta-grid supply via AESO P3102.
An AESO request is not an allocation.
Score
Sponsor Quality 14 / 15
Site & Approvals 18 / 20
Power Certainty 12 / 25
Commercial Commitment 5 / 20
Execution Evidence 12 / 20
Total 61 / 100
Scoring method. Not a credit rating or investment advice.