Kineticor Data Centre Campus
- Capacity
- Not publicly confirmed
- Investment
- Not publicly confirmed
- Score
- 27 / 100
- Checked
- Sep 11, 2026
DC Intel assessment
Speculative
Why
Useful negative control: the project had meaningful power work, but Rocky View County rejected the required ASP in September 2025, preventing the project from proceeding at that site.
Risk
Inactive after municipal planning rejection.
Watch
Only a materially revised/new site proposal would revive it.
Power strategy
Historic power work existed; site planning failed.
An AESO request is not an allocation.
Score
Sponsor Quality 10 / 15
Site & Approvals 0 / 20
Power Certainty 15 / 25
Commercial Commitment 2 / 20
Execution Evidence 0 / 20
Total 27 / 100
Scoring method. Not a credit rating or investment advice.