Teton Digital Northern Forge Campus
- Capacity
- 200 MW
- Investment
- Not publicly confirmed
- Score
- 63 / 100
- Checked
- Sep 11, 2026
Capacity basis: Proposed gas-to-compute capacity (MW)
DC Intel assessment
Probable
Why
Detailed site/power concept, environmental/water/consultation work and gas-supply arrangements are publicly described; staged 30 MW / 100 MW / 200 MW plan is more concrete than a pure announcement.
Risk
AUC approval, binding gas contracts, FID and customers are still needed; much evidence is proponent-supplied.
Watch
AUC approval, FID and binding gas/compute customer commitments.
Power strategy
Proposed 200 MW behind-the-meter natural-gas generation; future grid interconnect targeted.
An AESO request is not an allocation.
Score
Sponsor Quality 10 / 15
Site & Approvals 16 / 20
Power Certainty 17 / 25
Commercial Commitment 8 / 20
Execution Evidence 12 / 20
Total 63 / 100
Scoring method. Not a credit rating or investment advice.