Travers AI Data Centre Campus
- Capacity
- 2,000 MW
- Investment
- Not publicly confirmed
- Score
- 45 / 100
- Checked
- Sep 11, 2026
Capacity basis: Long-term planning target IT load (MW)
DC Intel assessment
Early-Stage
Why
Large defined site and active municipal/utility planning (rezoning, water licence, AltaLink/AESO studies) show a structured development process.
Risk
2 GW is a planning target; project is pre-development-permit with no tenant, FID or final transmission approvals.
Watch
Rezoning/land-use approval, AESO/AltaLink study advancement and Phase 1 financing/customer.
Power strategy
Proposed new 500 kV substation and two transmission feeds; Phase 1 concept ~500 MW.
An AESO request is not an allocation.
Score
Sponsor Quality 9 / 15
Site & Approvals 13 / 20
Power Certainty 11 / 25
Commercial Commitment 3 / 20
Execution Evidence 9 / 20
Total 45 / 100
Scoring method. Not a credit rating or investment advice.